ABOUT THE PROJECT

The City of Fort Worth and its project team is constructing an extension of Everman Parkway from Rosedale Springs Lane to Cameron Hill Point. Proposed improvements include a bridge over the Union Pacific Railroad (UPRR) and a crossing of Sycamore Creek. The project will also include a roundabout intersection at the future Hemphill Street extension.

The Road Ahead

Construction Phasing timeline*
Phase 1
Dec 2025 –
Jan 2027

Bridge over Union Pacific Railroad (UPRR) constructed.

Phase 2
Jan 2026 –
Sep/Oct 2027

Roundabout intersection constructed with a culvert box underneath at future Hemphill Street intersection.

Phase 3
Jun/Jul 2026 –
Jun/Jul 2027

Mainlanes constructed from west of the roundabout to Rosedale Springs Lane and mainlanes constructed east of the bridge to Cameron Hill Point. Roadway is anticipated to be open to traffic by end of 2027.

*Construction timeline is an estimate and is subject to change.

What to expect during construction

Common construction impacts & our approach to minimize disruptions
Construction Noise

Operation of machinery and vehicles.

How We Minimize It

Majority of work to take place during daytime hours; however, alternate work hours may be utilized when necessary to accelerate completion.
Dust and Debris

Airborne dirt and soil particles or debris.

How We Minimize It

Watering down soil and dusty areas within project work sites to keep dust from becoming airborne.

Large trash receptacles around the project area to maintain a clean job site.
Road Closures

Temporary blockages, lane closures or limited entry into businesses or residential areas.

How We Minimize It

Clear signage, signals, road markings and lighting.

Detour maps will be provided to the public in advance of any road closures.

Click here to sign up for construction notifications.
Traffic Delays

Lane reductions, slowed traffic in and out of residential areas and businesses.

How We Minimize It

Clear signage, barriers and fencing placed around project work site.

Trained personnel to maintain safe project site conditions.

Detour maps will be provided to the public in advance of any road closures.

Click here to sign up for construction notifications.
Safety

Construction zones with heavy equipment and restricted areas.

How We Minimize It

Clear signage, barriers and fencing placed around project work site.

Trained personnel to maintain safe project site conditions.
We understand construction can be inconvenient, and we’re committed to minimizing its impact to the extent possible.